Sheffield Resources Limited uploaded a News Release
September 18, 2023
Thunderbird Process Plant Commissioning Underway
Highlights:
- Process plant commissioning activities are underway, with forecast total project expenditure within the original $484m FID budget
- Dry Mining Unit (DMU) mobilised to Thunderbird site ahead of planned installation
- LNG storage tanks commissioned with power station commissioning underway
- First ore production on track for Q4 2023
- First delivery of mineral sands products to customers remains on target for Q1 2024