Thunderbird Construction Approaching 90% Complete

Highlights:

  • Construction activities are rapidly approaching 90% complete, with expected cost outcomes within the original planned $484m budget
  • Installation of major equipment including spirals, WHIMS, piping and electrical progressing well
  • Clearing and grubbing activities commenced by waste mining contractor, ahead of expected commencement of waste mining in Q3 2023
  • Operational readiness well advanced with progressive recruitment of key leadership personnel across all operational disciplines
  • Over 750,000 project labour hours completed LTI free
  • First delivery of mineral sands products to customers remains on target for Q1 2024