Sheffield Resources Limited uploaded a News Release
June 19, 2023
Thunderbird Construction Approaching 90% Complete
Highlights:
- Construction activities are rapidly approaching 90% complete, with expected cost outcomes within the original planned $484m budget
- Installation of major equipment including spirals, WHIMS, piping and electrical progressing well
- Clearing and grubbing activities commenced by waste mining contractor, ahead of expected commencement of waste mining in Q3 2023
- Operational readiness well advanced with progressive recruitment of key leadership personnel across all operational disciplines
- Over 750,000 project labour hours completed LTI free
- First delivery of mineral sands products to customers remains on target for Q1 2024