Sheffield Resources Limited uploaded a Corporate Update
January 23, 2024
Quarterly Activities Report for the period ended 31 December 2023
Thunderbird Mineral Sands Mine (Sheffield interest – 50%)
- Thunderbird mine commenced mining and processing operations
- Construction activities concluded during the quarter on time and within final investment decision (FID) budget of $484m
- Zero lost time incidents throughout construction, commissioning and initial operations
- Mining and processing ramp up performance above FID assumptions
- First export shipment of approximately 300 metric tonnes of non-magnetic concentrate dispatched following the end of the quarter
South Atlantic Project
- Drill line clearing and rig construction continued, with drilling to commence in the current March quarter
- Hatch appointed to undertake PFS for South Atlantic Project, with PFS scheduled for completion mid-2024
- Bujuru bulk sample test work results due in the current March quarter
Corporate
- Cash balance of $23.2m as at 31 December 2023 (unaudited)
- Investor & Shareholder Webinar – Tuesday, 23 January 2024 (refer link herein)