Sheffield Resources Limited uploaded a Presentation
August 10, 2023
Sheffield Resources Investor Presentation
Highlights:
Core Asset
- 50% interest Thunderbird Mineral Sands Project
- Stage 1 fully funded
- Construction over 90% complete
- On target for first customer deliveries in Q1 2024
- Stage 1 NPV8 $842m, generating ~$120m pa of cash to Sheffield following debt repayment (mid FY2027 in the base case)
KMS Growth
- Enhance KMS through
- Thunderbird Stage 2, incremental NPV8 of $548m
- Additional zones of mineralisation along a 120 km trend
- East Derby construction sand opportunity
South Atlantic
- South Atlantic Option
- Exploration Target ranging between 500 to 720Mt at 3.2 to 4.0% HM
- Exploration Targets comprising sulfate ilmenite and zircon
- Option Agreement executed with US$2.5m contribution to fund de-risking activities
Future Growth
- Review of other quality mineral sands opportunities
- Targeting advanced projects with potential to unlock value by applying Sheffield’s mineral sands and funding experience